Saturday, April 14, 2012

Status Update: 04/14/2012

Tasks Accomplished:

  • Team performed third party usability testing and received user feedback (1 Hour)
  • Team redesigned and modified application prototype (2 hours)
  • Boom created and refined new prototype (2 hours)
  • Team began designing implementation of application (2 hours)
  • Bill created high level architecture diagram for application based on team's design (1 hour)
  • Team members collaborated on preliminary design document (1 Hour)
  • Doug began updating SRS document (30 minutes)
  • Team continued Android API research and familiarization (45 minutes)
Next Week:
  • Elaborate on low-level details of design
  • Begin application implementation
Issues to Note:
  • Geoff will be out of town over the weekend, limiting his ability to contribute
  • Application implementation needs to be started soon
  • Design of application is fairly solid, but there are a few minor details to work out.