Status Update 04/22/2012

Tasks Accomplished:

  • Team began creation of Test Plan for system (4 hours)
  • Bill and Doug began implementing the prototype interface (3 hours)
  • Doug continued to update the SRS document (30 minutes)
Next Week:

  • Complete the Test Plan to solicit user feedback
  • Completely implement the prototype to use for testing

Issues to Note:

  • Implementation still at a very early stage
  • End of the quarter is nearing and members are becoming overloaded with other classwork