- Team began creation of Test Plan for system (4 hours)
- Bill and Doug began implementing the prototype interface (3 hours)
- Doug continued to update the SRS document (30 minutes)
- Complete the Test Plan to solicit user feedback
- Completely implement the prototype to use for testing
Issues to Note:
- Implementation still at a very early stage
- End of the quarter is nearing and members are becoming overloaded with other classwork