Sunday, May 6, 2012

Status Update 05/06/2012

Tasks Accomplished:

  • Doug and Bill finished prepping the prototype for usability evaluations (6 hours)
  • Geoff and Boom set up documentation and surveys for evaluations (3.5 hours)
  • Whole group performed user evaluations with third parties (4 hours)
Next Week:
  • Perform analysis of test results
  • Begin creation of project presentation
  • Make minor changes to prototype
  • Update any existing documentation
Issues to Note:
  • It was hard to find users to test the prototype, so information to analyze is scarce
  • Many members are bogged down with other classes and end-of-quarter projects